1What is a Bow-Tie?
The Bow-Tie (Bow-Tie) place l'top event at the centre of a bow-tie-shaped diagram: on the left, the causes that may lead to it, each intercepted by preventive barriers ; on the right, the consequences that may result, each mitigated by protective barriers. It is essentially a visual combination of a fault tree on the cause side and an event tree on the consequence side, focused on barriers rather than calculation.
Its strength is communication : a Bow-Tie diagram is much easier to read and present in a meeting than a HAZOP table or raw fault tree, while retaining equivalent analytical rigour.
2Method steps
- Define the top event โ the scenario's tipping point (e.g. loss of containment).
- List the causes on the left, often taken from an existing PHA, HAZOP, or safety report.
- Position preventive barriers between each cause and the top event.
- List the consequences that may occur on the right.
- Position protective barriers between the top event and each consequence.
- (advanced mode) Quantify โ cause probabilities, barrier PFDs, resulting probabilities, and minimal cut sets.
3Example completed in Polyodos
4Common mistakes
| Mistake | Why it is a problem |
|---|---|
| Counting the same barrier twice | A barrier shared by several cause or consequence paths must not be counted as if every path had its own independent protection. Double counting overstates actual risk control. |
| Mixing preventive and protective barriers | A preventive barrier acts before the top event, preventing escalation from the cause; a protective barrier acts after it, limiting the consequences. Placing barriers on the wrong side of the diagram distorts its meaning. |
| Confusing basic and advanced modes | Basic mode contains neither probabilities nor logic gates. Expecting a quantified risk calculation from it is a misunderstanding, not a limitation of the tool. |